Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Articles 6 and 16); Government Decree No. 214/2025/ND-CP da.
- Key Benchmark: 22/2023/QH15 and Clauses 1 and 2, Article 4 of Decree No.
- Execution Control: Collect signed independence and confidentiality declarations from all evaluation and appraisal panel members under Article 16.
01Regulatory Context & Core Scope
Safeguarding fair competition and preventing conflicts of interest serve as the primary defense against bid rigging from design preparation through contract award. Audit findings show that serious procurement violations frequently stem from retaining the same legal entity or mutually controlled companies for both design estimation and appraisal, or allowing a works bidder linked by majority equity to an E-HSMT consultant to compete.
Under Article 6 of Law on Procurement No. 22/2023/QH15 and Clauses 1 and 2, Article 4 of Decree No. 214/2025/ND-CP, legal and financial independence requires objective thresholds: firms cannot stand in a parent-subsidiary relationship; neither may hold more than 50% of shares or capital in the other; no common shareholder or organization may hold over 50% direct or indirect equity in both; and public service units cannot share the same direct governing authority.
02Independent Appraisal, Petitions & Audit Trails
For overlapping consulting assignments, Clauses 4 and 5, Article 4 of Decree No. 214/2025/ND-CP establish strict functional boundaries. While a consultant may perform multiple upstream or supervision roles within a project where legally permitted, for any single deliverable a firm may undertake only one of three tasks: drafting, design verification, or appraisal.
Thus, a consultant that prepares cost estimates or E-HSMT documents cannot conduct verification or independent appraisal on those exact deliverables.
03Core Regulatory Provisions & Conditions
Furthermore, Point a, Clause 2, Article 4 of Decree No. 214/2025/ND-CP strictly prohibits any firm that drafted, verified, or appraised an E-HSMT, or evaluated bids or appraised results for a works, goods, or non-consulting package, from submitting a bid on that package. Individual members of E-HSMT drafting or evaluation panels must also sign conflict-of-interest declarations confirming independence from competing bidders under Article 16 of the Procurement Law.
During independent E-HSMT and award appraisals under Circular No. 80/2025/TT-BTC, appraisal units should audit prior consulting contract awards alongside enterprise ownership records on the National Business Registration Portal and e-GP. Screening equity thresholds and legal representatives early prevents invalid awards caused by hidden financial ties.
Conflict-of-Interest Screening Checklist for Consulting and Bid Evaluation
- Compile a roster of all consulting firms engaged across survey, design, estimation, E-HSMT drafting, and appraisal.
- Enforce the one-of-three bar preventing any single firm from combining drafting, verification, and appraisal on the same deliverable.
- Check enterprise registration profiles for greater-than-50% common equity links between prior consultants and bidding firms.
- Collect signed independence and confidentiality declarations from all evaluation and appraisal panel members under Article 16.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Articles 6 and 16); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Article 4); Ministry of Finance Circulars No. 79/2025/TT-BTC dated 04/08/2025 and No. 80/2025/TT-BTC dated 08/08/2025.