Transitional Handling of Procurement Plans and E-HSMT Issued Before Law 90/2025/QH15 Took Effect

Transitional Handling of Procurement Plans and E-HSMT Issued Before Law 90/2025/QH15 Took Effect
Breakdown of the three transitional tracks under Clause 1, Article 10 of Law 90/2025/QH15 effective 1 July 2025 across closed tenders, open E-HSMTs, and pre-release procurement plans.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (amended by Law 57/2024/QH15); Law 90/2025/QH15 (Clause 1 Article 10, effective 1 July 2025).
  • Key Benchmark: Clause 1, Article 10 of Law 90/2025/QH15 sets three clear transitional rules keyed to package status on 1 July 2025.
  • Execution Control: Cite Clause 1, Article 10 of Law 90/2025/QH15 explicitly inside evaluation and appraisal preambles.

01Regulatory Context & Core Scope

During July 2025, thousands of ongoing public packages straddled the 1 July 2025 effective date of Law 90/2025/QH15 across different tender milestones. Misapplying new rules retroactively to closed bids or rigidly retaining old steps for unissued packages creates avoidable procedural challenges during post-award reviews.

02Effective Dates & Transitional Scope

Clause 1, Article 10 of Law 90/2025/QH15 sets three clear transitional rules keyed to package status on 1 July 2025. First, where an E-HSMT, E-HSMQT, E-HSMST, or HSYC was issued and closed or opened prior to 1 July 2025, evaluation, shortlist selection, contract award, and contract administration continue under Bidding Law 22/2023/QH15 (as amended by Law 57/2024/QH15) and prior implementing rules.

Second, where an E-HSMT or HSYC was released before 1 July 2025 but bid closing had not yet occurred, Project Owners may choose between two paths: proceeding under the already published tender documents and prior legal framework, or cancelling the notice to revise the contractor selection plan and E-HSMT under Law 90/2025/QH15.

03Qualification Benchmarks & Bidder Preferences

Third, where contractor selection plans were approved prior to 1 July 2025 without an E-HSMT or HSYC issued yet, Project Owners may amend the existing plan under the newly decentralized approval authority to take advantage of Law 90/2025/QH15 streamlining and expanded preference rules.

Throughout this July 2025 window while updated decrees and circulars replacing Decree 24/2024/ND-CP and Circular 22/2024/TT-BKHDT were pending release, Project Management Units should explicitly record E-TBMT publication dates and selected Clause 1, Article 10 transitional choices inside approval memos.

Three Transition Regimes on 01/07/2025 under Law 90/2025/QH15

Package Stage on 01/07/2025Governing FrameworkAuthorized Employer Action
Bid already closed before 01/07/2025Law 22/2023 & Law 57/2024Must complete evaluation and contract under prior rules
Issued before 01/07/2025 but not yet closedOption A (prior) or Option B (new Law 90)Continue prior dossier or cancel notice and revise
KHLCNT approved, E-HSMT not yet issuedLaw 90/2025/QH15Amend KHLCNT under decentralized authority and apply new rules

Law 90/2025/QH15 Transitional Compliance Checklist

  • Pinpoint E-HSMT publication and bid-closing timestamps relative to the 1 July 2025 cutoff date.
  • For packages closed before 1 July 2025, retain prior statutory citations consistently through contract award and management.
  • For open packages issued before 1 July 2025, issue a written decision electing either continuation or cancellation and re-issuance.
  • For pre-release approved plans, adjust plan terms under Project Owner authority where new Law 90/2025/QH15 provisions help.
  • Cite Clause 1, Article 10 of Law 90/2025/QH15 explicitly inside evaluation and appraisal preambles.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (amended by Law 57/2024/QH15); Law 90/2025/QH15 (Clause 1 Article 10, effective 1 July 2025); Decree 24/2024/ND-CP and Circular 22/2024/TT-BKHDT in transitional effect as of July 2025.