Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15 (Article 9), amended by Law 57/2024/QH15 and Law 90/2025/QH15; Decree 214/2025/ND-CP.
- Key Benchmark: Compile a timeline sheet matching plan approval dates, E-TBMT publication timestamps, and the statutory regime active at issuance.
- Execution Control: Enforce the minimum 5-year bidding archive under Article 9 of Law 22/2023/QH15 alongside financial retention periods under Circular 74/2025/TT-BTC.
01Regulatory Context & Core Scope
Vietnam's public procurement framework underwent two major regulatory shifts across 2025. Early in the year, Law 57/2024/QH15 (effective 15 January 2025) and Circular 23/2024/TT-BKHDT (effective 1 March 2025 prior to its replacement by Circular 80/2025/TT-BTC on 8 August 2025) addressed advance bidding and special contractor selection.
Mid-year, Law 90/2025/QH15, passed on 25 June 2025 and effective from 1 July 2025, decentralized contractor selection plan approval directly to Project Owners, removed mandatory plan appraisal steps, and expanded autonomous procurement authority for self-financed public service units.
02Security Validity & Commitment Scope
In August 2025, implementing decrees and circulars were replaced in sequence: Decree 214/2025/ND-CP and Circular 79/2025/TT-BTC took effect on 4 August 2025 (with online simplified works quotation starting on 1 September 2025), followed by Circular 80/2025/TT-BTC on 8 August 2025 and Ministry of Health Circular 40/2025/TT-BYT on 25 October 2025. At its year-end session, the National Assembly also passed Cybersecurity Law 116/2025/QH15 and High Technology Law 133/2025/QH15 on 10 December 2025, along with Law 142/2025/QH15 on 11 December 2025, carrying targeted Bidding Law amendments scheduled to take effect in 2026.
Because legal instruments shifted several times within a single fiscal year, project files frequently suffer from mixed statutory citations during State Audit or ministerial inspections. Whenever a contractor selection plan or E-HSMT was issued in June 2025 while bid evaluation and contract signing closed in September 2025, the archived dossier must record exact approval and e-GP publication timestamps to substantiate transitional compliance.
03Independent Appraisal, Petitions & Audit Trails
Under Article 9 of Bidding Law 22/2023/QH15, complete contractor selection records must be retained for at least 5 years from contract settlement or from the issuance date of a tender cancellation decision. Supporting accounting vouchers, electronic invoices, and final settlement schedules must simultaneously meet the 5-year, 10-year, or 20-year retention tiers established under Ministry of Finance Circular 74/2025/TT-BTC effective 18 August 2025.
To prepare efficiently for State Audit inspections, Project Owners and Project Management Units should lock a unified index linking wet-stamped physical approvals with verified e-GP exports, including electronic bid-opening minutes, clarification correspondence, bid-security extension logs, and original package budget quotations. Chronological indexing allows auditors to verify every approval milestone without re-auditing scattered folders.
Year-End Archiving Checklist for State Audit Readiness
- Compile a timeline sheet matching plan approval dates, E-TBMT publication timestamps, and the statutory regime active at issuance.
- Archive stamped PDF approvals alongside raw e-GP exports covering procurement plans, E-HSMT packages, addenda, and opening minutes.
- Segregate package budget substantiation files: approved cost estimates, public quotation requests, comparison tables, and valuation certificates.
- Preserve bid evaluation reports, clarification logs, document verification minutes, and independent award appraisal reports.
- Enforce the minimum 5-year bidding archive under Article 9 of Law 22/2023/QH15 alongside financial retention periods under Circular 74/2025/TT-BTC.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15 (Article 9), amended by Law 57/2024/QH15 and Law 90/2025/QH15; Decree 214/2025/ND-CP; Circular 79/2025/TT-BTC; Circular 80/2025/TT-BTC; Circular 74/2025/TT-BTC; Circular 40/2025/TT-BYT.