Policy & Procurement Law

Decree 214/2025/ND-CP Replaces Decree 24/2024/ND-CP Effective 4 August 2025: Core Regulatory Shifts

Decree 214/2025/ND-CP Replaces Decree 24/2024/ND-CP Effective 4 August 2025: Core Regulatory Shifts
Structured analysis of six major procurement reforms effective 4 August 2025 under Decree 214/2025/ND-CP spanning budget setting, direct appointment limits, online bidding, bid clarification, and vendor accountability.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (amended by Law 57/2024/QH15 and Law 90/2025/QH15); Decree 214/2025/ND-CP (replacing Decree 24/2024/ND-CP effective 4 August 2025).
  • Key Benchmark: First, Article 18 restructures package budget preparation.
  • Execution Control: Execute public e-GP quotation requests under Article 18 whenever establishing package budgets without fixed sector estimates.

01Regulatory Context & Core Scope

On 4 August 2025, the Government issued and enacted Decree 214/2025/ND-CP detailing implementation of the Bidding Law on contractor selection, fully replacing Decree 24/2024/ND-CP. The decree operationalizes reforms introduced by Law 57/2024/QH15 and Law 90/2025/QH15 to accelerate public capital disbursement and prune procedural bottlenecks.

02Pricing Methodology & Cost Controls

First, Article 18 restructures package budget preparation. Alongside approved cost estimates and similar contract awards within 12 months, Clause 2 codifies public e-GP quotation requests, clarifies accepting a minimum of one valid quote where competition is thin, and allows budget updates within 28 days before bid opening.

Second, financial ceilings for streamlined procurement expand significantly: Clause 4, Article 78 sets direct-appointment caps at VND 500 million (recurrent), VND 800 million (project consulting), and VND 2 billion (project goods, works, non-consulting, and mixed); Clause 4, Article 80 grants agency heads direct authority up to VND 50 million; and Clause 3, Article 99 opens simplified online quotations up to VND 2 billion (recurrent) and VND 5 billion (projects).

03Procedural Sequence & e-GP Execution

Third, bid evaluation and vendor accountability become sharper. Article 30 enables post-opening capability document clarifications and limits detailed works staff and equipment verification in domestic works, EC, and PC tenders to the first-ranked bidder. Simultaneously, Article 20 enforces triple bid securities for two years on bad-faith bidders while protecting contractors who refuse unlawful post-award contract additions.

Fourth, compliance burdens ease across contract execution and e-GP operations: Article 114 clarifies written amendment rules and waives addenda for routine unit-price quantity remeasurements; Articles 103 to 104 launch electronic catalog ordering; and Article 38 integrates domestic manufacturing and innovation preferences directly into scoring formulas.

Immediate Transition Checklist Under Decree 214/2025/ND-CP

  • Replace Decree 24/2024/ND-CP citations with Decree 214/2025/ND-CP across all approvals dated from 4 August 2025 onward.
  • Apply updated ceilings under Articles 78, 80, and 99 when drafting or amending contractor selection plans.
  • Limit key works staffing and equipment clarification requests to the top-ranked domestic bidder under Article 30.
  • Screen e-GP vendor reputation records under Article 20 before validating bid security sufficiency.
  • Execute public e-GP quotation requests under Article 18 whenever establishing package budgets without fixed sector estimates.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (amended by Law 57/2024/QH15 and Law 90/2025/QH15); Decree 214/2025/ND-CP (replacing Decree 24/2024/ND-CP effective 4 August 2025).