Key Takeaways
- Governing Scope: Construction Law No. 135/2025/QH15; Ministry of Construction Circular No. 34/2026/TT-BXD dated 25/06/2026, effective 01/07/2026 (Articles 4 and 5).
- Key Benchmark: For projects mid-appraisal at the cutoff, Clause 2, Article 5 splits into two branches.
- Execution Control: State explicitly in the evaluation report which building-grade circular governs each submitted reference contract.
01Regulatory Context & Core Scope
Immediately after Circular No. 34/2026/TT-BXD took effect on 01/07/2026, a common error in E-HSMT drafting and similar-contract evaluation was applying the new grading schedules indiscriminately regardless of project approval dates. Article 5 of Circular No. 34/2026/TT-BXD establishes explicit transitional rules to preserve legal certainty for projects initiated before 01/07/2026.
02Contract Performance, Settlement & Amendments
Under Clause 1, Article 5 of Circular No. 34/2026/TT-BXD, building grades for construction investment projects approved by investment decision prior to 01/07/2026 continue to follow the law in force at the date of investment approval, notably Circular No. 06/2021/TT-BXD as amended by Circular No. 02/2025/TT-BXD depending on approval timing. This prevents retroactive disruption to approved designs, acceptance authorities, and tender qualification baselines.
For projects mid-appraisal at the cutoff, Clause 2, Article 5 splits into two branches. Where a project or adjusted feasibility study was submitted to the specialized construction authority before 01/07/2026 and satisfied submission completeness without an appraisal notice yet issued, grading follows the rules effective at submission; where the dossier failed completeness or appraisal found it unready for approval, grading shifts to Circular No. 34/2026/TT-BXD.
03Qualification Benchmarks & Bidder Preferences
Where an older approved project undergoes construction design revision from 01/07/2026 onward, Clause 3, Article 5 creates a strict technical test. Under Point a, revisions that leave building importance, capacity scale, and structural scale unchanged retain the grade set at original investment approval; under Point b, any revision altering importance, capacity scale, or structural scale triggers re-determination under Circular No. 34/2026/TT-BXD.
Consequently, bid evaluation panels assessing reference works contracts after July 2026 should record both the legal instrument governing the current tender and the instrument governing each submitted reference contract based on its respective investment approval date. Documenting that distinction protects Pass or Fail conclusions during appraisal and subsequent state audits.
Construction Grade Transition Matrix under Article 5 Circular 34/2026/TT-BXD
| Project Status on 01/07/2026 | Clause | Applicable Grade Determination Standard |
|---|---|---|
| Investment approved before 01/07/2026 | Clause 1 Art. 5 | Retain Circular 06/2021 & Circular 02/2025/TT-BXD effective at approval |
| Submitted for appraisal before 01/07/2026 | Clause 2 Art. 5 | Use regulation in force at eligible appraisal submission date |
| Design adjusted from 01/07/2026 | Clause 3 Art. 5 | Keep prior grade if capacity unchanged; re-grade under Circular 34/2026 if modified |
Article 5 Transitional Review Checklist Under Circular 34/2026/TT-BXD
- Verify the investment approval decision date to classify projects before versus from 01/07/2026.
- For dossiers submitted for appraisal before 01/07/2026, retain formal completeness confirmation proving eligibility under prior rules.
- Check design-revision approvals issued from 01/07/2026 for changes to capacity or structural scale under Point b, Clause 3, Article 5.
- State explicitly in the evaluation report which building-grade circular governs each submitted reference contract.
Legal Basis & Regulatory Scope
Construction Law No. 135/2025/QH15; Ministry of Construction Circular No. 34/2026/TT-BXD dated 25/06/2026, effective 01/07/2026 (Articles 4 and 5); transitional application of Circular No. 06/2021/TT-BXD (as amended by Circular No. 02/2025/TT-BXD) for projects approved prior to 01/07/2026 under Clause 1, Article 5 of Circular No. 34/2026/TT-BXD; Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025.