Tendering Construction Works Insurance and Independent Final Settlement Audit Consulting Packages

Tendering Construction Works Insurance and Independent Final Settlement Audit Consulting Packages
Guidance on pricing and E-HSMT drafting under Decree 67/2023/ND-CP for mandatory construction insurance and Decree 254/2025/ND-CP for independent project settlement audit consulting.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15; Decree 214/2025/ND-CP.
  • Key Benchmark: Verify mandatory construction insurance applicability under Decree 67/2023/ND-CP and set minimum coverage equal to full contract value.
  • Execution Control: Include audit firm obligations to support settlement review clarifications and re-audits under Article 35 of Decree 254/2025/ND-CP.

01Regulatory Context & Core Scope

Within construction project administrative budgets, mandatory construction works insurance (non-consulting services) and independent final settlement audit consulting represent specialized packages governed by strict sectoral rules beyond general bidding thresholds.

02Pricing Methodology & Cost Controls

For construction works insurance, Decree 67/2023/ND-CP mandates coverage for works materially affecting public safety and community interests, environmentally sensitive projects, and large or technically complex structures. The minimum insured sum must equal the full completed value of the works (covering materials, labor, installed equipment, freight, taxes, and fees) and cannot fall below the total construction contract value including approved addenda.

When budgeting and drafting an insurance E-HSMT under Circular 79/2025/TT-BTC, Project Owners reference statutory premium tables and deductibles in the Decree 67/2023/ND-CP Annexes (under which insurers may adjust premiums upward or downward by up to 25% based on risk profile). Even where works contracts assign insurance purchase to the construction contractor, the Project Owner must verify valid coverage prior to site mobilization.

03Validity Boundaries & Common Evaluation Pitfalls

For independent project settlement audits, Decree 254/2025/ND-CP took effect on 26 September 2025, replacing Decree 99/2021/ND-CP on public-investment payment and final settlement. Under Article 35 and related settlement provisions of Decree 254/2025/ND-CP, independent audit reports anchor final settlement verification, and the reviewing authority retains power to mandate supplemental or re-performed audits if omissions surface.

When tendering settlement audit services using Form 6A of Circular 79/2025/TT-BTC or direct appointment within Decree 214/2025/ND-CP ceilings, the E-HSMT must enforce strict conflict-of-interest barriers confirming the audit firm holds no equity ties and performed no design, cost estimation, or site supervision roles on the audited project.

Works Insurance & Settlement Audit Tender Checklist

  • Verify mandatory construction insurance applicability under Decree 67/2023/ND-CP and set minimum coverage equal to full contract value.
  • Calibrate insurance package budgets using statutory fee schedules within the 25% risk adjustment band.
  • Cite Decree 254/2025/ND-CP (effective 26 September 2025) as the active legal basis for public-investment settlement audits.
  • Embed strict conflict-of-interest exclusions barring firms involved in project design, budgeting, or supervision.
  • Include audit firm obligations to support settlement review clarifications and re-audits under Article 35 of Decree 254/2025/ND-CP.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15; Decree 214/2025/ND-CP; Decree 67/2023/ND-CP; Decree 254/2025/ND-CP (Article 35, effective 26 September 2025); Circular 79/2025/TT-BTC.

Filed under: Sectoral Tenders (Health, IT, Works) #Works Insurance #Settlement Audit #Decree 67/2023 #Decree 254/2025
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.