Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15; Decree 254/2025/ND-CP (Articles 8 and 9, effective 26 September 2025).
- Key Benchmark: Under Clause 2, Article 8, Treasury disbursement submissions require payment requests, withdrawal orders, and original or certified Advance Payment Guarantees.
- Execution Control: Collect advance-guarantee extensions at least 15 days prior to expiry whenever recovery remains incomplete.
01Regulatory Context & Core Scope
Contract advance payments provide essential working capital for initial material procurement and site mobilization, yet carry high public-fund exposure when advance guarantees and staged deductions are loosely enforced. Since 26 September 2025, advance disbursements and recovery in public-investment projects follow Decree 254/2025/ND-CP, which replaced Decree 99/2021/ND-CP.
02Security Validity & Commitment Scope
Under Article 9 of Decree 254/2025/ND-CP, advances may be released only after the contract enters into force, site handover prerequisites are satisfied for civil works, and the Project Owner receives a valid Advance Payment Guarantee matching the advance amount (mandatory above contractual thresholds, such as advances exceeding VND 1 billion in construction contracts). Notably, Decree 254/2025/ND-CP moves away from a single rigid statutory ceiling across all contracts, letting Project Owners and contractors agree advance rates tailored to sectoral rules and realistic execution schedules.
Under Clause 2, Article 8, Treasury disbursement submissions require payment requests, withdrawal orders, and original or certified Advance Payment Guarantees. Bank advance guarantees must remain valid until full recovery of the advanced principal, typically allowing progressive face-value reduction proportional to recovered amounts certified in interim payments.
03Core Regulatory Provisions & Conditions
Contract drafters should embed an explicit advance-recovery formula in the E-HSMT draft contract, commonly accelerating deductions so the advance reaches zero by the time cumulative certified payments reach 80% of contract value. If contract completion extends, Project Owners must secure advance-guarantee extensions well ahead of bank expiry dates.
A recurring operational pitfall occurs when Project Management Units disburse mobilization advances without auditing early material procurement or factory fabrication milestones, creating overdue advance balances across fiscal year-end audits.
5-Gate Advance Payment & Guarantee Control Checklist
- Confirm contract effectiveness and site handover documentation before approving initial advance disbursement.
- Verify the bank Advance Payment Guarantee matches the disbursed sum and remains valid until full recovery.
- Submit payment applications, Treasury withdrawal forms, and advance guarantees per Clause 2, Article 8 of Decree 254/2025/ND-CP.
- Enforce staged interim payment deductions targeting complete recovery before cumulative payments hit 80% of contract value.
- Collect advance-guarantee extensions at least 15 days prior to expiry whenever recovery remains incomplete.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15; Decree 254/2025/ND-CP (Articles 8 and 9, effective 26 September 2025); Decree 37/2015/ND-CP as amended by Decree 50/2021/ND-CP.