Key Takeaways
- Governing Scope: Articles 39 and 64 (Clauses 1, 2, and 3) of Bidding Law 22/2023/QH15; Chapter VIII (Articles 105, 106, and 107) of Decree 24/2024/ND-CP.
- Key Benchmark: For multi-year civil infrastructure exposed to material, fuel, and labor price volatility, Clause 3, Article 64 provides for adjustable unit-price contracts.
- Execution Control: Define clear addendum procedures for actual measured quantity variations under unit-price contracts.
01Regulatory Context & Core Scope
Contract type is a mandatory element established inside the procurement plan under Article 39 of Bidding Law 22/2023/QH15. Selecting a contract structure mismatched with design maturity or market volatility frequently creates disputes during quantity measurement, variation approvals, and payment settlement.
02Effective Dates & Transitional Scope
Under Clause 1, Article 64 of the Bidding Law, lump-sum contracts suit packages where work scope, technical specifications, and schedule are well defined with minimal expected quantity changes, as well as EPC or turnkey packages governed by output specifications. Both the package estimate and bid prices must incorporate contingencies for quantity risk and price escalation, with progress payments tied to contract percentages or completed milestones.
When technical requirements and unit rates are clear but exact quantities remain uncertain at tender stage, such as foundation piling, dredging, or refurbishment of existing facilities, Clause 2, Article 64 authorizes fixed unit-price contracts. Under Articles 105 and 106 of Decree 24/2024/ND-CP, unit rates remain locked throughout execution while actual verified quantities may increase or decrease via formal contract addenda.
03Contract Performance, Settlement & Amendments
For multi-year civil infrastructure exposed to material, fuel, and labor price volatility, Clause 3, Article 64 provides for adjustable unit-price contracts. In accordance with Article 107 of Decree 24/2024/ND-CP and Circular 22/2024/TT-BKHDT templates, the draft contract must predefine the adjustment formula, official price index source, and base index date before bids are invited.
In practice, VNTender often structures mixed contracts combining lump-sum pricing for standardized equipment supply with fixed unit pricing for site installation works subject to field conditions. Clearly delineating payment boundaries across separate bills of quantities inside E-HSMT minimizes post-award ambiguity during supervision and final settlement.
Contract Type Selection under Article 64 Bidding Law 2023
| Contract Type | Suitable Project Scope | Payment & Adjustment Mechanism |
|---|---|---|
| Lump-Sum (Clause 1) | Well-defined scope, low volume variance, EPC | Paid by percentage or milestone; contingencies priced in |
| Fixed Unit Price (Clause 2) | Clear specs & rates but uncertain actual quantities | Unit prices stay fixed; quantities adjusted per verified acceptance |
| Adjustable Unit Price (Clause 3) | Multi-year infrastructure exposed to material volatility | Rates adjusted via preset formula and official price indices |
Checklist for Selecting Contract Types in Procurement Plans
- Assess construction drawing completeness and bill-of-quantities certainty before proposing a lump-sum contract.
- Evaluate contract duration and key input price volatility when considering adjustable unit-price structures.
- Embed explicit price adjustment formulas, official index sources, and base dates inside E-HSMT draft contracts.
- Define clear addendum procedures for actual measured quantity variations under unit-price contracts.
Legal Basis & Regulatory Scope
Articles 39 and 64 (Clauses 1, 2, and 3) of Bidding Law 22/2023/QH15; Chapter VIII (Articles 105, 106, and 107) of Decree 24/2024/ND-CP; Circular 22/2024/TT-BKHDT.