Key Takeaways
- Governing Scope: Point i, Clause 2 of Article 50, and Articles 65, 67, and 68 of Bidding Law 22/2023/QH15; Articles 34, 35, and 141 of Decree 214/2025/ND-CP (as amended by Articles 3.
- Key Benchmark: Substantively, finalization must respect the boundaries of Article 34 of Decree 214/2025/ND-CP.
- Execution Control: Publish key contract data within 5 working days and update milestone progress and subcontractor changes under Article 3 of Decree 349/2026/ND-CP.
01Regulatory Context & Core Scope
Finalizing and executing electronic contracts on e-GP directly connects procurement records with State Treasury disbursement workflows under Article 10 of Circular 79/2025/TT-BTC. Under Clause 1, Article 32 of Circular 79/2025/TT-BTC, contracts awarded via open bidding, restricted bidding, competitive shopping, online quotation, or online shopping funded through the State Treasury must be executed electronically on e-GP pursuant to Point i, Clause 2, Article 50 of Bidding Law 22/2023/QH15.
A common drafting mistake is pasting Special Conditions of Contract text directly into the main Contract Agreement, creating duplicate or conflicting terms upon digital signature. Clauses 2 and 4, Article 32 of Circular 79/2025/TT-BTC organize the e-contract package into four signed parts (the Agreement, fully completed Special Conditions reflecting all clarifications and finalization terms, scope and price schedules, and other annexes) and instruct drafters not to repeat completed Special Conditions inside the Agreement.
02Security Validity & Commitment Scope
Substantively, finalization must respect the boundaries of Article 34 of Decree 214/2025/ND-CP. Neither party may introduce demands departing from the E-HSMT, accepted E-HSDT, or award decision; where a Project Owner insists on unagreed obligations, Clause 4 entitles the bidder to refuse without forfeiting bid security or suffering reputation penalties.
Subcontractor lists and ceiling percentages must also be locked in before signing under Clause 2, Article 141 of Decree 214/2025/ND-CP as amended by Article 17 of Decree 349/2026/ND-CP.
03Pricing Methodology & Cost Controls
Before executing digital signatures on e-GP, confirm that every joint venture member signs (or holds valid authorization per Clause 3, Article 67 of the Bidding Law) and that Performance Security is posted before or upon contract effectiveness under Clause 3, Article 68. Reviewing bank account numbers, tax codes, and unit-rate totals prevents Treasury payment rejections.
Once effective, the Project Owner must publish key contract particulars on e-GP within 5 working days under Article 12 of Circular 79/2025/TT-BTC and keep actual milestone progress and subcontractor updates current under Clause 2, Article 35 of Decree 214/2025/ND-CP as amended by Article 3 of Decree 349/2026/ND-CP.
Checklist for Reviewing Electronic Contracts Prior to e-GP Digital Signing
- Populate all accepted clarifications and finalization terms into Special Conditions without duplicating them in the main Agreement.
- Verify digital signatures across all joint venture members alongside bank account details and tax IDs required for State Treasury links.
- Confirm Performance Security delivery prior to or upon contract effectiveness and finalize subcontractor scope limits.
- Publish key contract data within 5 working days and update milestone progress and subcontractor changes under Article 3 of Decree 349/2026/ND-CP.
Legal Basis & Regulatory Scope
Point i, Clause 2 of Article 50, and Articles 65, 67, and 68 of Bidding Law 22/2023/QH15; Articles 34, 35, and 141 of Decree 214/2025/ND-CP (as amended by Articles 3 and 17 of Decree 349/2026/ND-CP); and Articles 10, 12, and 32 of Circular 79/2025/TT-BTC.