Policy & Procurement Law

Overview of Core Reforms in the Newly Passed Bidding Law 22/2023/QH15

Overview of Core Reforms in the Newly Passed Bidding Law 22/2023/QH15
Overview of key reforms in Bidding Law 22/2023/QH15 passed on 23 June 2023 (taking effect 1 January 2024): Chapter V healthcare procurement relief, advance bidding, and e-GP digitization.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect on 1 January 2024 (Articles 5, 14, 16, 23, 36, 42, Chapter V, Articles 95, and 96); active 2023 tenders r.
  • Key Benchmark: It also establishes an optional repeat-order clause capped at 30% of initial contract quantities.
  • Execution Control: Plan professional procurement certification readiness for evaluation and appraisal personnel ahead of 1 January 2024.

01Regulatory Context & Core Scope

On 23 June 2023, Vietnam's National Assembly passed Bidding Law 22/2023/QH15 comprising 10 Chapters and 96 Articles, scheduled under Article 95 to take effect on 1 January 2024 and replace Bidding Law 43/2013/QH13. Throughout the second half of 2023, active tenders remain governed by Law 43/2013/QH13, Decree 63/2014/ND-CP, and Circular 08/2022/TT-BKHDT while Project Owners prepare for the 2024 statutory transition.

02Sector Technical Rules & Supporting Evidence

One of the most anticipated reforms is Chapter V, dedicated exclusively to procuring pharmaceuticals, reagents, testing consumables, and medical equipment. It authorizes price negotiation, centralized purchasing, reagent tenders bundled with vendor-placed analyzers, and emergency procurement flexibility for public hospitals.

On project planning and execution speed, Law 22/2023/QH15 introduces Master Contractor Selection Plans under Article 36 for complex investments and advance bidding under Article 42 permitting pre-approval tendering up to award identification. It also establishes an optional repeat-order clause capped at 30% of initial contract quantities.

03Security Validity & Commitment Scope

Regarding bidder participation and securities, the law shortens bid-security return deadlines to 14 days under Article 14, grants household businesses legal bidder status under Article 5, and codifies 09 prohibited conduct groups under Article 16 alongside comprehensive e-GP disclosure of contract performance.

During the July to December 2023 preparation period, Hoang Quan Construction Development Investment Consulting Co., Ltd. (VNTender) advises Project Owners to monitor upcoming implementing decrees and manage E-HSMT release schedules carefully under Article 96 ahead of 1 January 2024.

Six Preparation Priorities Ahead of Bidding Law 22/2023/QH15

  • Audit late-2023 project schedules to distinguish packages issued under Law 43/2013/QH13 from those shifting into 2024.
  • Update internal finance workflows to enforce the new 14-day maximum bid-security release timeline under Article 14.
  • Evaluate advance bidding under Article 42 and 30% repeat-order options for upcoming investment projects.
  • Plan professional procurement certification readiness for evaluation and appraisal personnel ahead of 1 January 2024.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect on 1 January 2024 (Articles 5, 14, 16, 23, 36, 42, Chapter V, Articles 95, and 96); active 2023 tenders remain under Law 43/2013/QH13, Decree 63/2014/ND-CP, and Circular 08/2022/TT-BKHDT.

Filed under: Policy & Procurement Law #Law 22/2023/QH15 #2023 Law Reforms #Healthcare Tenders #e-Procurement
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.