Contracts & Pricing

Applying the 30 Percent Additional Purchase Option in Goods and Healthcare Supply Contracts

Applying the 30 Percent Additional Purchase Option in Goods and Healthcare Supply Contracts
Explaining legal conditions for exercising the 30% additional purchase option under Clause 8, Article 39 of Bidding Law 2023 and Clause 11, Article 24 of Decree 24/2024/ND-CP from KHLCNT planning through contract addenda.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (Point c, Clause 2, Article 39; Clause 8, Article 39).
  • Key Benchmark: Clause 11, Article 24 of Decree 24/2024/ND-CP further requires the bidding document to specify the maximum optional quantities matching the approved plan.
  • Execution Control: Confirm unit prices do not exceed base contract rates and execute the addendum while the contract remains valid.

01Regulatory Context & Core Scope

For pharmaceuticals, medical consumables, and recurring goods with fluctuating demand, the additional purchase option under Clause 8, Article 39 of Bidding Law 22/2023/QH15 enables Project Owners to scale quantities without launching a separate tender. Exercising this flexibility lawfully requires building the option into the procurement plan from the start.

02Pricing Methodology & Cost Controls

Under Point c, Clause 2, Article 39 of Bidding Law 22/2023/QH15, the approved tender package ceiling excludes the value of the additional purchase option, yet the procurement plan must state the estimated quantity and value of that option. Clause 11, Article 24 of Decree 24/2024/ND-CP further requires the bidding document to specify the maximum optional quantities matching the approved plan.

During contract performance, activating the option requires satisfying all five statutory conditions in Point c, Clause 8, Article 39. The contractor must have been selected via open bidding or price negotiation, the additional volume may not exceed 30% of the corresponding contract line-item quantity, and an approved budget estimate must cover the added purchase.

03Contract Performance, Settlement & Amendments

The fourth and fifth conditions strictly govern pricing and timing: unit prices for additional deliveries must not exceed the unit prices signed in the base contract, and the option must be exercised while the primary contract remains valid. Expired contracts or upward unit-price adjustments fall outside the statutory scope of an additional purchase option.

To formalize execution, the parties sign a contract addendum under Article 106 of Decree 24/2024/ND-CP and adjust performance security proportionally if required. In public hospitals, monitoring consumption run-rates monthly ensures the 30% option is executed well before base-contract expiration to prevent supply interruptions.

Five Statutory Conditions for the 30% Additional Purchase Option

Mandatory ConditionLegal CeilingVerification Point
Original MethodOpen bidding or price negotiationDisclosed in KHLCNT and E-HSMT (excluded from base budget)
Additional Quantity CapMaximum 30% of corresponding line-item volumeBefore drafting contract addendum under Article 106
Unit Price & Contract ValidityMust not exceed signed unit price while base contract activeProhibited once main contract term expires

Checklist for Exercising the 30% Option

  • Confirm the procurement plan and E-HSMT explicitly stated maximum optional quantities and estimated values.
  • Verify the base contract was awarded through open bidding or price negotiation.
  • Check that added quantities stay within 30% per contract item and have an approved budget allocation.
  • Confirm unit prices do not exceed base contract rates and execute the addendum while the contract remains valid.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (Point c, Clause 2, Article 39; Clause 8, Article 39); Decree 24/2024/ND-CP dated 27 February 2024 (Clause 11, Article 24; Article 106).

Filed under: Contracts & Pricing #Additional Purchase Option #30% Ceiling #Goods Contracts #Medical Procurement
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.