Handling Contractor Requests to Change Origin or Substitute Equivalent Product Models During Goods Contract Execution

Handling Contractor Requests to Change Origin or Substitute Equivalent Product Models During Goods Contract Execution
Five mandatory rules under Clause 27, Article 131 of Decree 24/2024/ND-CP for newer-version product replacements (same maker, same origin, no price rise) and origin-change limits under Article 70 of Law 22/2023/QH15.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (Article 70); Decree 24/2024/ND-CP dated 27 February 2024 (Article 106 and Clause 27, Article 131).
  • Key Benchmark: Clause 27, Article 131 of Decree 24/2024/ND-CP creates a formal path for approving newer-generation or newer-year product models when all five cumulative conditions are satisfied.
  • Execution Control: Ensure replacement unit prices do not exceed contract rates and sign the addendum prior to delivery.

01Regulatory Context & Core Scope

Between bid closing and final delivery in IT, medical, and MEP equipment contracts, global manufacturers frequently discontinue legacy product codes or release updated hardware revisions. Delivering goods bearing a different model number or country of origin without formal approval will fail site acceptance and expose the Project Owner to state-audit disallowances.

02Core Regulatory Provisions & Conditions

Clause 27, Article 131 of Decree 24/2024/ND-CP creates a formal path for approving newer-generation or newer-year product models when all five cumulative conditions are satisfied. First, the contractor must submit a formal written request to the Project Owner; second, the replacement goods must come from the same manufacturer and carry the exact same country of origin stated in the contract.

The remaining three conditions under Clause 27, Article 131 require that technical features, configurations, and performance parameters match or exceed the contracted product, align with the Project Owner's operational needs, and carry a unit price no higher than the signed contract unit rate. Missing any one of these five elements bars routine model replacement under Clause 27.

03Evaluation Criteria & Documentary Proof

Where a contractor seeks to change the country of origin itself, for instance due to factory relocation or supply-chain disruption, the expedited Clause 27 path fails the same-origin rule. Any origin change must then be assessed strictly under contract-amendment rules in Article 70 of Bidding Law 22/2023/QH15 and Article 106 of Decree 24/2024/ND-CP, requiring explicit contractual allowance or an objective fundamental change of circumstances that neither compromises evaluation equity nor breaches price ceilings.

Before executing a contract addendum, the contractor should provide an official manufacturer end-of-life and successor letter alongside a line-by-line technical comparison matrix. The Project Owner's technical committee must verify equal or superior specifications, confirm unchanged contract pricing, and execute the addendum prior to shipment or customs clearance.

Contract Goods Substitution Verification Checklist

  • Require a formal contractor request backed by an official manufacturer discontinuation and successor letter.
  • Verify identical manufacturer and identical country of origin when applying Clause 27, Article 131.
  • Compile a parameter-by-parameter technical review proving equal or superior performance and functional fit.
  • Ensure replacement unit prices do not exceed contract rates and sign the addendum prior to delivery.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (Article 70); Decree 24/2024/ND-CP dated 27 February 2024 (Article 106 and Clause 27, Article 131).

Filed under: Contracts & Pricing #Model Substitution #Clause 27 Art 131 Decree 24 #Contract Amendment #Same Country of Origin