Key Takeaways
- Governing Scope: Bidding Law 43/2013/QH13 (Clause 3, Article 33 and Point k, Clause 6, Article 89) and Decree 63/2014/ND-CP (in force in 2023); Bidding Law 22/2023/QH15 passed 23 Jun.
- Key Benchmark: This prohibition carries forward strictly into Point l, Clause 6, Article 16 of Bidding Law 22/2023/QH15, passed on 23 June 2023 and taking effect on 1 January 2024.
- Execution Control: Align upcoming 2024 packaging plans against Point l, Clause 6, Article 16 of Bidding Law 22/2023/QH15.
01Regulatory Context & Core Scope
During procurement plan appraisals and public expenditure audits, one of the most frequent compliance violations is splitting an integrated supply or repair requirement into multiple sub-packages just below VND 100 million or VND 500 million to qualify for direct appointment instead of open competitive bidding.
02Pricing Methodology & Cost Controls
Under Clause 3, Article 33 of Bidding Law 43/2013/QH13 active in 2023, dividing a project into tender packages must rest strictly on technical characteristics, execution sequence, overall project synchronization, and rational scale. Point k, Clause 6, Article 89 of Law 43/2013/QH13 explicitly prohibits splitting projects or procurement budgets unlawfully to trigger direct appointment or restrict bidder participation.
This prohibition carries forward strictly into Point l, Clause 6, Article 16 of Bidding Law 22/2023/QH15, passed on 23 June 2023 and taking effect on 1 January 2024. Because Law 22/2023/QH15 further narrows recurrent procurement direct appointment to packages above VND 50 million up to VND 100 million, artificial slicing to avoid e-GP open bidding becomes even more exposed.
03Contract Performance, Settlement & Amendments
Auditors and inspectors detect unlawful splitting through three converging indicators: separated packages share identical technical categories or supply families; approval, contracting, and acceptance occur closely within the same quarter or fiscal year; and each sliced estimate clusters immediately beneath statutory direct-appointment ceilings under Decree 63/2014/ND-CP.
During independent plan appraisals, VNTender audits annual procurement budgets holistically so items sharing technical nature and delivery schedules are consolidated into competitive open-tender packages rather than fragmented sub-threshold contracts.
Appraisal Checklist Against Unlawful Contract Splitting
- Audit the entire annual approved budget inventory before approving individual sub-package selection plans.
- Verify genuine technical, sequencing, and synchronization grounds under Clause 3, Article 33 of Law 43/2013/QH13 whenever splitting scopes.
- Flag and consolidate concurrent same-category requests priced suspiciously just below direct-appointment limits.
- Align upcoming 2024 packaging plans against Point l, Clause 6, Article 16 of Bidding Law 22/2023/QH15.
Legal Basis & Regulatory Scope
Bidding Law 43/2013/QH13 (Clause 3, Article 33 and Point k, Clause 6, Article 89) and Decree 63/2014/ND-CP (in force in 2023); Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect on 1 January 2024 (Point l, Clause 6, Article 16).