Key Takeaways
- Governing Scope: Bidding Law 43/2013/QH13 and Decree 63/2014/ND-CP (in force in 2023); Construction Law 50/2014/QH13 (Clause 28, Article 3 and Point d, Clause 2, Article 86).
- Key Benchmark: Article 20 of Decree 06/2021/ND-CP further specifies field clarification, design revision, and completion-acceptance responsibilities.
- Execution Control: Recognize approved design handover certificates as valid completion proof when assessing similar consulting contracts.
01Regulatory Context & Core Scope
When preparing contractor selection plans and draft design consulting contracts, project teams frequently dispute when the contract period officially ends. Folding the entire downstream construction timeline into the design package duration on account of author supervision stretches design contracts across years, complicating guarantee extensions and completed-contract qualifications.
02Procedural Sequence & e-GP Execution
Under Clause 28, Article 3 and Point d, Clause 2, Article 86 of Construction Law 50/2014/QH13, author supervision is a statutory duty performed by the designer during construction to verify works follow approved drawings. Article 20 of Decree 06/2021/ND-CP further specifies field clarification, design revision, and completion-acceptance responsibilities.
Under Articles 3 and 15 of Decree 37/2015/ND-CP alongside procurement rules, the formal duration of a design consulting contract runs from contract effectiveness until final acceptance and handover of approved design drawings and cost estimates. The tender selection plan duration excludes subsequent construction-phase author supervision.
03Effective Dates & Transitional Scope
Retaining a small final installment (for example 5% of contract value) until overall construction completion operates as performance security for post-delivery author supervision obligations, comparable to construction defect retention. That retention milestone does not extend the design delivery schedule when drawings and estimates were delivered on time.
Accordingly, when drafting E-HSMTs for design services or evaluating prior similar contracts, VNTender advises defining two distinct contractual milestones: approved design handover duration (representing the tender contract period) and post-handover author supervision tied to actual site construction.
Checklist Separating Design Duration From Author Supervision
- State design contract duration strictly from contract effectiveness through handover of approved design and estimate documents.
- Include a separate contract clause detailing ongoing author supervision obligations during construction under Law 50/2014/QH13.
- Distinguish design-handover payment milestones from retention held for construction-phase author supervision.
- Recognize approved design handover certificates as valid completion proof when assessing similar consulting contracts.
Legal Basis & Regulatory Scope
Bidding Law 43/2013/QH13 and Decree 63/2014/ND-CP (in force in 2023); Construction Law 50/2014/QH13 (Clause 28, Article 3 and Point d, Clause 2, Article 86); Decree 37/2015/ND-CP (Articles 3 and 15); Decree 06/2021/ND-CP (Article 20).