Centralized Procurement at Ministerial and Provincial Levels: Framework Agreements and Direct Contracts With Beneficiary Units

Centralized Procurement at Ministerial and Provincial Levels: Framework Agreements and Direct Contracts With Beneficiary Units
Detailing the two centralized procurement models under Article 53 of the Procurement Law and Chapter VI of Decree 214/2025/ND-CP, mandatory framework terms, and payment restrictions.

Key Takeaways

  • Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Article 53); Government Decree No. 214/2025/ND-CP dated 04/.
  • Key Benchmark: Confirm the active status and maximum 36-month validity term of the published e-GP framework agreement before initiating standalone purchases.
  • Execution Control: Verify statutory exceptions under Clauses 22 and 23, Article 140 of Decree No. 214/2025/ND-CP before contracting outside an active framework.

01Regulatory Context & Core Scope

Ministerial and provincial centralized procurement consolidates dispersed purchasing demand across hospitals, schools, and administrative agencies to standardize technical specs and optimize public spending. Under Article 53 of Law on Procurement No. 22/2023/QH15 and Chapter VI (Articles 89 through 92) of Decree No. 214/2025/ND-CP, designated centralized-procurement items must follow a disciplined workflow from demand aggregation to contract execution at beneficiary entities.

Clause 4, Article 53 of Law No. 22/2023/QH15 establishes two centralized procurement execution models. Under the first model, the centralized purchasing unit aggregates demand, runs the tender, signs the contract directly, and delivers to end users.

02Security Validity & Commitment Scope

Under the second model, widely used by ministries and provincial departments, the centralized unit conducts the tender and executes a framework agreement with one or more winning suppliers, enabling beneficiary entities to sign direct supply contracts thereunder.

Under Clause 2, Article 92 of Decree No. 214/2025/ND-CP, a framework agreement must cover 11 mandatory items (Points a through l): scope of goods or services; expected delivery or service schedule and locations; handover, advance payment, settlement, and contract liquidation terms; pricing for each item or service; warranty, maintenance, training, and user-guidance terms; contractor duties including contract signing and performance security obligations; duties of procuring user units; duties of the centralized purchasing unit; framework validity period (capped at 36 months under Clause 3, Article 92); liquidated damages and breach compensation; and other related terms.

03Core Regulatory Provisions & Conditions

While a framework agreement remains active, beneficiary units requiring covered goods or services must sign direct contracts with the selected framework suppliers at the locked-in prices, scope, and terms. Should an end-user entity independently contract with an outside vendor despite an active framework agreement, the State Treasury and financial control agencies will withhold payment unless an explicit exception applies under Clauses 22 and 23, Article 140 of Decree No. 214/2025/ND-CP.

In practice, payment delays frequently arise when beneficiary contracts drift from the delivery schedules, pricing, or acceptance conditions recorded in the master framework agreement. Beneficiary entities should reproduce exact supply scope, unit prices, handover rules, warranty terms, and party obligations verbatim from the signed framework agreement into each direct contract and attach the centralized award notice to support smooth Treasury disbursement.

Checklist for Direct Contracts Under Centralized Framework Agreements

  • Confirm the active status and maximum 36-month validity term of the published e-GP framework agreement before initiating standalone purchases.
  • Verify that all 11 mandatory items (Points a through l, Clause 2, Article 92 of Decree No. 214/2025/ND-CP) appear in the framework agreement.
  • Reproduce exact supply scope, pricing, handover terms, warranty rules, and performance-security duties from the framework agreement inside each direct contract.
  • Verify statutory exceptions under Clauses 22 and 23, Article 140 of Decree No. 214/2025/ND-CP before contracting outside an active framework.

Legal Basis & Regulatory Scope

Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Article 53); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Chapter VI, Articles 89 to 92; Clauses 22 and 23, Article 140); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025.

Filed under: Contracts & Pricing #Centralized Procurement #Framework Agreement #Direct Contract #Decree 214/2025