Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15 dated 23 June 2023 (Article 39); Government Decree 24/2024/ND-CP dated 27 February 2024 (Article 16, replacing Decree 63/2014/ND-CP).
- Key Benchmark: A major relief under Point d, Clause 2, Article 16 permits collecting a minimum of 01 quotation instead of mandating three quotes where market supply is narrow.
- Execution Control: Archive public request proofs, signed vendor quotations, and validity dates in the official budget approval file.
01Regulatory Context & Core Scope
Government Decree 24/2024/ND-CP took immediate effect on 27 February 2024, replacing Decree 63/2014/ND-CP to operationalize Bidding Law 22/2023/QH15. Article 16 directly resolves persistent price-setting bottlenecks for Project Owners, especially public hospitals and agencies buying specialized technical equipment.
02Pricing Methodology & Cost Controls
Clause 2, Article 16 of Decree 24/2024/ND-CP enumerates 07 permitted data sources for establishing package estimates: approved cost estimates; consultant scope and expert man-month rates; historical awarded contract prices; supplier market quotations; public-asset valuation rules; statutory rates and fee schedules; and officially declared or listed prices.
A major relief under Point d, Clause 2, Article 16 permits collecting a minimum of 01 quotation instead of mandating three quotes where market supply is narrow. Gathering multiple quotations remains encouraged; for general goods and services with two or more valid quotes, the Project Owner computes the average price while ensuring open and transparent solicitation.
03Qualification Benchmarks & Bidder Preferences
For healthcare packages covering pharmaceuticals, reagents, laboratory consumables, and medical devices, Point d requires posting quotation requests for at least 10 days on e-GP, the Project Owner's portal, the Ministry of Health portal, or the medical device public service portal. Where two or more responsive quotes arrive, hospitals may select the highest quotation consistent with budget capacity and clinical standards rather than being forced onto the lowest-cost option.
During dossier preparation, consulting teams should archive invitation logs, screenshots proving the 10-day posting window where applicable, technical equivalence comparison tables, and clear breakdowns of VAT and installation services. Complete audit trails protect Project Owners during independent appraisal and state audit reviews.
Checklist for Quotation Solicitation Under Article 16
- Select the appropriate pricing basis among the 07 sources in Clause 2, Article 16 of Decree 24/2024/ND-CP before drafting estimates.
- Verify the mandatory 10-day public posting window on authorized portals for medical goods and equipment packages.
- Normalize technical specs, delivery terms, warranty scope, and VAT across all received quotes prior to averaging or selecting ceilings.
- Archive public request proofs, signed vendor quotations, and validity dates in the official budget approval file.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15 dated 23 June 2023 (Article 39); Government Decree 24/2024/ND-CP dated 27 February 2024 (Article 16, replacing Decree 63/2014/ND-CP).