Key Takeaways
- Governing Scope: Decree 24/2024/ND-CP dated 27 February 2024 (Article 24); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Article 4.
- Key Benchmark: Contracts under 12 months apply a flat requirement equal to 30% of the approved package budget.
- Execution Control: Verify proportional allocation rules for average revenue and financial capacity across joint venture members.
01Regulatory Context & Core Scope
When drafting civil-works E-HSMT packages under Form 3A (one-envelope) or Form 3B (two-envelope) of Circular 06/2024/TT-BKHDT, two financial metrics frequently cause drafting errors: minimum average annual construction revenue and package financial resources. Setting thresholds above standard guidance risks competition-restriction challenges, while miscalculating duration conversions delays appraisal approval.
02Pricing Methodology & Cost Controls
For average annual construction revenue (excluding VAT), Chapter III of Forms 3A and 3B typically sets a 3-to-5-year lookback prior to bid closing. Where contract duration is 12 months or longer, the baseline requirement equals the VAT-exclusive package budget divided by contract duration in years, multiplied by factor k (normally between 1.5 and 2); for contracts under 12 months, the threshold is calibrated proportionally without exceeding reasonable bounds.
Where a bidder has operated for fewer years than the stated lookback window, its average annual revenue is calculated over its actual years in operation and passes if that average meets the threshold. If bid closing falls before the statutory annual tax filing deadline in the first quarter, lookback years shift back by one fiscal year per template notes; household businesses prove revenue via verified tax payment records.
03Core Regulatory Provisions & Conditions
For package financial resources, contracts lasting 12 months or more apply the formula t multiplied by the package budget divided by contract duration in months, where t is typically set at 3 (representing three months of working capital). Contracts under 12 months apply a flat requirement equal to 30% of the approved package budget.
Bidders demonstrate financial resources through liquid assets, available credit facilities, or binding credit commitments issued by licensed financial institutions in Vietnam. Because e-GP pulls corporate financial statement metrics from 2021 onward automatically via the National Business Registration System, evaluation panels should pay special attention to checking scanned bank credit commitment letters when relied upon.
Works E-HSMT Financial Formula Checklist
- Use VAT-exclusive package value in the average annual revenue formula and set factor k between 1.5 and 2.
- Check whether duration is 12+ months (t = 3 monthly run-rate) or under 12 months (30% of package budget) for financial resources.
- Retain standard template footnotes covering recently established firms and Q1 closing-date shifts.
- Verify proportional allocation rules for average revenue and financial capacity across joint venture members.
Legal Basis & Regulatory Scope
Decree 24/2024/ND-CP dated 27 February 2024 (Article 24); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Article 4; Chapter III of Forms 3A and 3B).