Key Takeaways
- Governing Scope: Articles 37 through 41 and Clauses 1 and 5 of Article 50 of Bidding Law 22/2023/QH15; Article 97 of Decree 24/2024/ND-CP.
- Key Benchmark: Approval workflows should follow Article 40 for investment projects and Article 41 for recurrent procurement estimates to avoid misrouting submissions.
- Execution Control: Publish approved procurement plans on e-GP within five working days under Article 13 of Circular 22/2024/TT-BKHDT.
01Regulatory Context & Core Scope
Late December 2024 marks the peak preparation window for public agencies, public service units, and project management boards finalizing procurement plans for 2025 budget allocations. Unlike 2024, when a 500,000,000,000 VND ceiling applied under Clause 8, Article 97 of Decree 24/2024/ND-CP, Clause 1, Article 50 of Bidding Law 22/2023/QH15 mandates full online tendering from 1 January 2025.
02Qualification Benchmarks & Bidder Preferences
Specifically, effective 1 January 2025, all domestic open bidding, restricted bidding, and competitive shopping packages must run on the national e-GP platform regardless of package value. Statutory exceptions remain restricted under Clause 5, Article 50 to two-stage methods, international tenders, direct contracting, direct shopping, self-execution, state-secret packages, or packages exceeding e-GP technical capacity.
Under Articles 37 and 38 of the Bidding Law, planners must structure package divisions around technical coherence and project sequencing while strictly avoiding artificial splitting to bypass competitive e-bidding. All seven statutory components under Article 39 including package title, budget, funding source, selection method, start timeline, contract type, and duration must reconcile cleanly with approved 2025 budget decisions.
03Pricing Methodology & Cost Controls
Approval workflows should follow Article 40 for investment projects and Article 41 for recurrent procurement estimates to avoid misrouting submissions. Once approved, Article 13 of Circular 22/2024/TT-BKHDT requires uploading the procurement plan onto e-GP within five working days from the decision date.
For plans submitted in late December 2024 whose tenders will launch in early 2025, VNTender advises preparing submissions on Form 02A of Circular 22/2024/TT-BKHDT, which enters full effect on 1 January 2025, ensuring seamless continuity into the new fiscal year.
Pre-Submission Checklist for 2025 Procurement Plans
- Route all 2025 domestic open, restricted, and competitive shopping packages through e-GP per Clause 1, Article 50.
- Reconcile funding allocations and approved 2025 budget estimates before locking package values under Articles 38 and 39.
- Confirm whether approval authority follows Article 40 (investment projects) or Article 41 (procurement estimates).
- Publish approved procurement plans on e-GP within five working days under Article 13 of Circular 22/2024/TT-BKHDT.
Legal Basis & Regulatory Scope
Articles 37 through 41 and Clauses 1 and 5 of Article 50 of Bidding Law 22/2023/QH15; Article 97 of Decree 24/2024/ND-CP; Articles 4 and 13 of Circular 22/2024/TT-BKHDT (taking full effect on 1 January 2025).