Independent E-HSMT Appraisal Before Issuance: Common Restrictive Criteria Flagged in Audits

Independent E-HSMT Appraisal Before Issuance: Common Restrictive Criteria Flagged in Audits
Identifying restrictive E-HSMT clauses commonly flagged in procurement inspections under Clause 3, Article 44 of the Bidding Law, Article 129 of Decree 24/2024, and Annex 10 of Circular 22/2024.

Key Takeaways

  • Governing Scope: Clause 6, Article 16 and Clauses 3 and 4, Article 44 of Bidding Law 22/2023/QH15; Article 129 of Decree 24/2024/ND-CP.
  • Key Benchmark: Under Clause 4, Article 44 of the Bidding Law, any issued E-HSMT condition breaching Clause 3 is legally void and cannot be relied upon to disqualify an E-HSDT.
  • Execution Control: Issue the appraisal report on Form 3A of Circular 23/2024/TT-BKHDT documenting required edits prior to publication.

01Regulatory Context & Core Scope

Independent E-HSMT appraisal under Article 129 of Decree 24/2024/ND-CP and Form 3A of Circular 23/2024/TT-BKHDT serves as the decisive quality filter before tender notices go live on e-GP. Procurement audits repeatedly reveal that most bidder petitions and bid cancellations stem from superficial reviews that fail to catch restrictive qualification or technical clauses.

02Validity Boundaries & Common Evaluation Pitfalls

Under Clause 6, Article 16 and Clause 3, Article 44 of Bidding Law 22/2023/QH15, E-HSMT documents must never impose terms that restrict bidder participation or favor particular suppliers to create unfair competition. While Circular 22/2024/TT-BKHDT governs standard forms, appraisal panels should systematically benchmark draft criteria against the restrictive-clause list set out in Annex 10 of that Circular.

The most frequent violation involves specifying unauthorized brand names, single-country origins, or cherry-picked technical parameters matching a single manufacturer catalog when no compatibility exception applies. A second recurring defect is inflating similar-contract thresholds, annual revenue ratios, or key personnel credentials beyond the actual scale and technical grade of the works.

03Qualification Benchmarks & Bidder Preferences

A third category covers demanding manufacturer authorization letters for standard off-the-shelf commodities or requiring mandatory site-visit certificates and local office presence as pass-fail hurdles. Requiring personnel experience strictly within a specific province or identical agency sector also draws audit citations for narrowing open competition.

Under Clause 4, Article 44 of the Bidding Law, any issued E-HSMT condition breaching Clause 3 is legally void and cannot be relied upon to disqualify an E-HSDT. Before recommending E-HSMT approval on e-GP, appraisal teams should inspect consistency across qualification matrices, technical specifications, and webform bills of quantities.

Anti-Restriction Checklist for E-HSMT Appraisal

  • Audit technical specifications against Annex 10 of Circular 22/2024/TT-BKHDT to remove single-brand parameters.
  • Verify similar-contract values and construction grades match the package grade without artificial escalation.
  • Remove manufacturer authorization mandates for standard commodities and eliminate geographic experience barriers.
  • Issue the appraisal report on Form 3A of Circular 23/2024/TT-BKHDT documenting required edits prior to publication.

Legal Basis & Regulatory Scope

Clause 6, Article 16 and Clauses 3 and 4, Article 44 of Bidding Law 22/2023/QH15; Article 129 of Decree 24/2024/ND-CP; Annex 10 of Circular 22/2024/TT-BKHDT; Form 3A of Circular 23/2024/TT-BKHDT.

Filed under: Appraisal, Petitions & e-GP #E-HSMT Appraisal #Competition Restriction #Clause 3 Article 44 #Form 3A Circular 23