Key Takeaways
- Governing Scope: Article 64 of Bidding Law 22/2023/QH15; Clause 1 of Article 16 and Article 29 of Decree 24/2024/ND-CP.
- Key Benchmark: Align contingency treatment in the price schedule strictly with lump-sum, fixed unit-price, or adjustable contract rules.
- Execution Control: State in the draft contract that provisional and contingency funds disburse only against formally approved variation orders.
01Regulatory Context & Core Scope
When structuring package budgets and webform bills of quantities on e-GP for works or mixed contracts, drafters frequently debate how contingencies and provisional sums should appear in bidder price schedules. Misalignment between package estimates and financial ranking formulas easily distorts bid comparisons if bidders alter locked provisional figures or apply discounts broadly.
02Pricing Methodology & Cost Controls
Under Clause 1, Article 16 of Decree 24/2024/ND-CP, the package budget must account fully for all execution expenses, including quantity contingencies, price-escalation contingencies, taxes, fees, and levies. Specifically for construction works using fixed unit-price or adjustable unit-price contracts, contingencies incorporate provisional sums where applicable and may be drawn solely when verified variations occur.
Under Circular 22/2024/TT-BKHDT templates, lump-sum contracts require bidders to embed quantity and price-escalation risks directly inside their quoted item rates rather than listing a separate contingency line. By contrast, when a unit-price E-HSMT designates fixed provisional sums inside the summary price schedule, bidders must enter the exact owner-specified figure without cutting it to gain an artificial price advantage.
03Procedural Sequence & e-GP Execution
During financial evaluation on e-GP, the evaluation panel must verify whether E-HSMT Chapter III excludes uniform provisional sums and general contingencies during bid ranking. Standard works templates strip out owner-fixed provisional items during price comparison so rankings reflect true competitive pricing on core work items, adding them back into the contract ceiling only where applicable.
If a bidder omits a mandatory provisional sum or applies a blanket percentage discount across fixed contingency lines, the evaluation panel must apply deviation corrections under Decree 24/2024/ND-CP or clarify that discounts apply exclusively to core bid items. Tight BoQ formatting upfront avoids settlement conflicts with Treasury disbursement officers later.
Checklist for Contingencies and Provisional Sums in E-HSMT and Evaluation
- Align contingency treatment in the price schedule strictly with lump-sum, fixed unit-price, or adjustable contract rules.
- Lock or instruct bidders not to alter owner-specified provisional sums in the e-GP summary schedule.
- Exclude uniform provisional sums and general contingencies when calculating comparison prices if specified in Chapter III.
- State in the draft contract that provisional and contingency funds disburse only against formally approved variation orders.
Legal Basis & Regulatory Scope
Article 64 of Bidding Law 22/2023/QH15; Clause 1 of Article 16 and Article 29 of Decree 24/2024/ND-CP; Circular 22/2024/TT-BKHDT.