Key Takeaways
- Governing Scope: Circular 22/2024/TT-BKHDT dated 17 November 2024 of the Ministry of Planning and Investment (Articles 16, 18, 20, and 33); Circular 06/2024/TT-BKHDT dated 26 April 2.
- Key Benchmark: Clause 1, Article 33 of Circular 22/2024/TT-BKHDT sets two distinct effective dates.
- Execution Control: Cross-check all webform fields prior to clicking online approval since e-GP locks synchronized package data upon sign-off.
01Regulatory Context & Core Scope
On 17 November 2024, the Ministry of Planning and Investment issued Circular 22/2024/TT-BKHDT governing e-GP procurement disclosures and standard bidding documents. The circular takes full effect on 1 January 2025 to replace Circular 06/2024/TT-BKHDT, while introducing an early commencement track for online system approvals from 1 December 2024.
02Core Regulatory Provisions & Conditions
Clause 1, Article 33 of Circular 22/2024/TT-BKHDT sets two distinct effective dates. Specifically, Clause 1 of Article 16, Clause 1 of Article 18, Clause 1 of Article 20, and related provisions on online approval of solicitation documents and selection outcomes take effect early on 1 December 2024, one month before the remaining provisions enter into force on 1 January 2025.
From 1 December 2024, project owners execute approvals for E-HSMQT, E-HSMST, E-HSMT, prequalification outcomes, and award results directly inside the e-GP portal using authorized user roles and valid digital signatures. Direct electronic sign-off eliminates redundant print, wet-stamp, and PDF re-upload steps.
03Procedural Sequence & e-GP Execution
Organizations preparing for the December rollout should audit role assignments between Project Owner and Procuring Entity accounts and verify public USB token validity on e-GP. Direct online approvals rely on synchronized webform fields covering package ceilings, schedules, and evaluation rules before notice publication.
For packages published between 20 November 2024 and 31 December 2024, standard E-HSMT templates under Circular 06/2024/TT-BKHDT continue to apply until 31 December 2024. Procurement teams should separate internal readiness into two tracks: activating e-GP digital signature workflows on 1 December 2024 and adopting the new Circular 22/2024/TT-BKHDT templates from 1 January 2025.
Readiness Checklist for Circular 22/2024/TT-BKHDT
- Verify Project Owner e-GP account permissions and active digital certificates before 1 December 2024.
- Align internal appraisal sign-offs with direct online approval of E-HSMT and award outcomes starting 1 December 2024.
- Keep Circular 06/2024/TT-BKHDT templates for remaining 2024 postings while preparing new templates for 1 January 2025.
- Cross-check all webform fields prior to clicking online approval since e-GP locks synchronized package data upon sign-off.
Legal Basis & Regulatory Scope
Circular 22/2024/TT-BKHDT dated 17 November 2024 of the Ministry of Planning and Investment (Articles 16, 18, 20, and 33); Circular 06/2024/TT-BKHDT dated 26 April 2024 (applicable through 31 December 2024).