Ordinary and Simplified Online Quotation Procedures Under Decree 24/2024/ND-CP

Ordinary and Simplified Online Quotation Procedures Under Decree 24/2024/ND-CP
Distinguishing eligibility limits, notice periods, bid security rules, and minimum 24-hour bidding windows between ordinary and simplified online quotation under Articles 98, 100, and 101 of Decree 24/2024/ND-CP.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 dated 23 June 2023 (Clause 2, Article 20); Government Decree 24/2024/ND-CP dated 27 February 2024 (Articles 98, 99, 100, and 101).
  • Key Benchmark: Under Article 101 of Decree 24/2024/ND-CP, simplified online quotation omits full E-HSMT preparation and waives bid security.
  • Execution Control: Publish complete technical specs, origin rules, and delivery terms at least 03 working days prior to simplified session launch.

01Regulatory Context & Core Scope

Decree 24/2024/ND-CP operationalizes online quotation on the National e-Procurement System under Articles 98, 99, 100, and 101, introducing real-time price competition for standardized goods and non-consulting services. Selecting the correct variant during procurement planning depends on clearly distinguishing ordinary online quotation from the simplified track.

02Security Validity & Commitment Scope

Under Clause 2, Article 98 and Article 100 of Decree 24/2024/ND-CP, ordinary online quotation applies to simple non-consulting services and standardized off-the-shelf goods evaluated primarily on price. This track still requires a full E-HSMT and bid security, with the live bidding window of at least 24 hours occurring at the financial stage only for technically compliant bidders.

By contrast, Clause 3, Article 98 limits simplified online quotation to three cases: goods or non-consulting packages under recurrent procurement budgets up to VND 300 million; project packages under public investment or state-owned enterprise projects up to VND 1 billion; and proprietary-brand purchases needed for technological compatibility, copyright, or warranty preservation where multiple vendors can supply.

03Pricing Methodology & Cost Controls

Under Article 101 of Decree 24/2024/ND-CP, simplified online quotation omits full E-HSMT preparation and waives bid security. The procuring entity posts an invitation notice on e-GP at least 03 working days before the session starts, stating technical specs, delivery terms, and bid decrements, followed by a minimum 24-hour bidding window displaying live ranked prices anonymously.

Once the simplified session closes, e-GP ranks bids automatically so the evaluation panel only verifies eligibility and technical compliance of the lowest-ranked bidder before award approval. This workflow shortens cycle times for routine equipment and consumables while keeping unit pricing transparent.

Standard vs Simplified Online Quotation (Decree 24/2024/ND-CP)

DimensionStandard Online Quotation (Art. 100)Simplified Online Quotation (Art. 98, 101)
Value ThresholdStandardized goods & simple non-consulting<= VND 300M (recurrent) or <= VND 1B (project)
E-HSMT & Bid SecurityE-HSMT & bid security requiredNo complex E-HSMT; no bid security required
Notice & Bidding WindowFinancial bidding phase >= 24 hoursNotice >= 03 working days prior; live bidding >= 24 hours

Checklist for Organizing Online Quotations on e-GP

  • Verify package ceilings (VND 300 million for recurrent budgets or VND 1 billion for projects) before selecting the simplified track.
  • Configure clear bid decrement increments and ensure the live quotation window runs for at least 24 continuous hours.
  • Confirm no bid security is requested in tender notices issued under the simplified online quotation procedure.
  • Publish complete technical specs, origin rules, and delivery terms at least 03 working days prior to simplified session launch.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 dated 23 June 2023 (Clause 2, Article 20); Government Decree 24/2024/ND-CP dated 27 February 2024 (Articles 98, 99, 100, and 101).

Filed under: Appraisal, Petitions & e-GP #Online Quotation #e-GP Platform #Decree 24/2024 #Goods Procurement