Common Errors and Administrative Risks From Late Contract and Addendum Publication on e-GP

Common Errors and Administrative Risks From Late Contract and Addendum Publication on e-GP
Reviewing the mandatory 5-working-day contract disclosure deadline on e-GP, addendum update workflows, and administrative penalties under Decree 122/2021/ND-CP.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (Clause 4 Article 8); Decree 214/2025/ND-CP.
  • Key Benchmark: Set a mandatory 5-working-day calendar alert from contract effective date to complete e-GP core contract publication.
  • Execution Control: Observe organizational fine thresholds of VND 15M to 20M under Article 36 of Decree 122/2021/ND-CP for late filings.

01Regulatory Context & Core Scope

While many Project Management Units manage E-HSDT evaluation and award approvals carefully, post-award e-GP disclosure frequently slips once contracts are signed. Procurement inspections consistently identify delayed contract publication and omitted addenda updates as top administrative compliance failures.

02Procedural Sequence & e-GP Execution

Under Clause 4, Article 8 of Bidding Law 22/2023/QH15, implemented via Decree 214/2025/ND-CP and Circular 79/2025/TT-BTC, Project Owners must publish core contract particulars on e-GP within 5 working days from the date the contract takes effect. This obligation applies to both electronic and offline packages subject to the Bidding Law unless classified as state secrets.

Whenever subsequent execution requires schedule extension addenda, price revisions, or scope adjustments, contract administrators must promptly update the e-GP contract execution module accordingly. Leaving only the original contract record on the portal creates discrepancies against final payment values and actual completion dates during audit verification.

03Core Regulatory Provisions & Conditions

Under Article 36 of Decree 122/2021/ND-CP governing administrative sanctions in planning and investment, failing to meet statutory publication deadlines carries organizational fines of VND 15 million to VND 20 million (and half that range for individuals under Clause 2, Article 4), escalating to VND 30 million to VND 50 million for complete failure to publish.

To enforce compliance automatically, Project Owners should require contract officers to attach the e-GP publication confirmation receipt inside the payment file before releasing advance-payment paperwork to accounting, locking in adherence to the 5-working-day clock.

Contract & Addendum e-GP Publication Checklist

  • Set a mandatory 5-working-day calendar alert from contract effective date to complete e-GP core contract publication.
  • Cross-check contract number, signing date, awarded price, duration, and legal vendor name prior to publishing.
  • Upload contract amendment addenda or termination notices promptly inside the e-GP contract management module.
  • Require the e-GP publication confirmation screenshot inside the initial advance payment voucher packet.
  • Observe organizational fine thresholds of VND 15M to 20M under Article 36 of Decree 122/2021/ND-CP for late filings.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (Clause 4 Article 8); Decree 214/2025/ND-CP; Circular 79/2025/TT-BTC; Decree 122/2021/ND-CP (Clause 2 Article 4 and Article 36).

Filed under: Appraisal, Petitions & e-GP #Contract Publication #e-GP Portal #Statutory Deadlines #Contract Addenda
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.