Key Takeaways
- Governing Scope: Article 45 of Bidding Law 22/2023/QH15; Decree 24/2024/ND-CP.
- Key Benchmark: Under Article 45 of Bidding Law 22/2023/QH15, E-HSMT amendments must be issued at least 10 days before the bid-closing date on standard packages.
- Execution Control: Verify post-extension E-HSDT and bid-security validity dates for all submissions after opening.
01Regulatory Context & Core Scope
While an E-HSMT is live on e-GP, bidder clarification queries frequently expose specification typos or bill-of-quantities mismatches only days before closing. Publishing an E-HSMT amendment without extending the closing deadline to satisfy mandatory notice periods invites formal bidder petitions or forced tender cancellation.
02Core Regulatory Provisions & Conditions
Under Article 45 of Bidding Law 22/2023/QH15, E-HSMT amendments must be issued at least 10 days before the bid-closing date on standard packages. For small-scale packages comprising works or mixed tenders up to 20,000,000,000 VND and goods or non-consulting tenders up to 10,000,000,000 VND, the minimum pre-closing notice period is three working days.
Whenever an amendment becomes necessary inside that 10-day or 3-working-day window, the Project Owner must simultaneously extend the bid-closing date. The revised closing deadline must leave at least the full statutory minimum period measured from the e-GP publication timestamp of the amendment so all bidders can revise their proposals fairly.
03Procedural Sequence & e-GP Execution
Under Articles 18 and 19 of Circular 22/2024/TT-BKHDT, whose online e-GP approval rules entered early enforcement on 1 December 2024, the Project Owner must digitally sign the E-HSMT amendment approval on e-GP, attach the formal amendment decision, and update the closing timestamp in the E-TBMT notice. All webform schedules and attachments must stay synchronized.
Crucially, extending the closing date shifts every downstream deadline tied to bid closing, including E-HSDT validity and bid-security start and expiry dates. During post-opening review, evaluation panels must confirm whether early submitters updated their bank guarantees to cover the extended timeline.
Checklist for E-HSMT Amendments and Closing-Date Extensions on e-GP
- Check package budget against the 10-billion and 20-billion VND small-package thresholds to determine the 10-day or 3-working-day minimum.
- Approve the E-HSMT amendment and set a new closing timestamp providing the full statutory period after e-GP upload.
- Execute online amendment approval and E-TBMT extension updates under Articles 18 and 19 of Circular 22/2024/TT-BKHDT.
- Verify post-extension E-HSDT and bid-security validity dates for all submissions after opening.
Legal Basis & Regulatory Scope
Article 45 of Bidding Law 22/2023/QH15; Decree 24/2024/ND-CP; Articles 18, 19, and Clause 1 of Article 33 of Circular 22/2024/TT-BKHDT (early approval rules effective 1 December 2024).