Key Takeaways
- Internal execution only: The 0.2% and 0.1% schedule (2M to 3M floor, 60M cap) covers solely Project Owner internal expert and appraisal panels.
- Independent consultants: Under Point a Clause 2 Art. 14 Decree 214/2025, fees are exempt from Clauses 3 to 7 and follow Circular 7/2026/TT-BNV salary norms plus market quotes.
01. Why Percentage Caps Only Cover Internal Execution
Under Article 14 of Decree 214/2025/ND-CP dated 4 August 2025, contractor selection cost formulas are strictly divided into two tracks: direct internal execution by Project Owner panels and outsourced independent procurement consulting.
02. Track 1: Project Owner Internal Expert & Appraisal Panels (Clauses 4 to 7)
When the Project Owner directly assigns qualified internal staff, fee ceilings apply as a percentage of package price:
- E-HSMT or E-HSYC preparation (Point c Clause 4): 0.2% of package budget (min 3,000,000 VND, max 60,000,000 VND).
- E-HSMT or E-HSYC appraisal (Point d Clause 4): 0.1% of package budget (min 2,000,000 VND, max 60,000,000 VND).
- E-HSDT evaluation (Point b Clause 5): 0.2% of package budget (min 3,000,000 VND, max 60,000,000 VND).
- Selection result appraisal (Clause 6): 0.1% of package budget (min 3,000,000 VND, max 60,000,000 VND), including unsuccessful tenders.
- Re-tender or similar packages (Clause 7): Document drafting and appraisal fees are capped at 50% of Clause 4 rates.
03. Track 2: Hiring an Independent Procurement Consultant (Point a Clause 2 & Circular 7/2026/TT-BNV)
Point a, Clause 2, Article 14 explicitly states that when hiring a procurement consultant, consulting fees are NOT bound by the rates in Clauses 3, 4, 5, 6, and 7. Instead, estimates are prepared using scope man-days, market consulting quotes, and Article 3 of Circular 7/2026/TT-BNV (effective 1 July 2026, replacing Circular 004/2025/TT-BNV on a 26-working-day monthly basis): Level 1 max 70,000,000 VND/month, Level 2 max 55,000,000 VND/month, Level 3 max 40,000,000 VND/month, and Level 4 max 30,000,000 VND/month, plus statutory management, employer insurance, logistics, and VAT.
Try both estimation modes instantly in the VNTender 2026 Cost & Consultant Salary Calculator.
Legal Basis & Regulatory Scope
Point a Clause 2 and Clauses 4 to 7 Article 14 of Decree 214/2025/ND-CP dated 04/08/2025; Article 3 of Circular 7/2026/TT-BNV dated 05/05/2026 (effective 01/07/2026).
Nghị định số 214/2025/NĐ-CP; Thông tư số 7/2026/TT-BNV