Chính sách và Pháp luật

Distinguishing Internal Procurement Costs and Independent Consultant Fees Under Article 14 of Decree 214/2025/ND-CP

Clarifying Article 14 of Decree 214/2025/ND-CP: the 0.2% and 0.1% schedule (capped at 60M VND) applies strictly to internal Project Owner execution; hiring an independent procurement consultant is exempt from those caps under Point a Clause 2 Article 14 and follows Circular 7/2026/TT-BNV expert salaries.

Distinguishing Internal Procurement Costs and Independent Consultant Fees Under Article 14 of Decree 214/2025/ND-CP

Key Takeaways

  • Internal execution only: The 0.2% and 0.1% schedule (2M to 3M floor, 60M cap) covers solely Project Owner internal expert and appraisal panels.
  • Independent consultants: Under Point a Clause 2 Art. 14 Decree 214/2025, fees are exempt from Clauses 3 to 7 and follow Circular 7/2026/TT-BNV salary norms plus market quotes.

01. Why Percentage Caps Only Cover Internal Execution

Under Article 14 of Decree 214/2025/ND-CP dated 4 August 2025, contractor selection cost formulas are strictly divided into two tracks: direct internal execution by Project Owner panels and outsourced independent procurement consulting.

02. Track 1: Project Owner Internal Expert & Appraisal Panels (Clauses 4 to 7)

When the Project Owner directly assigns qualified internal staff, fee ceilings apply as a percentage of package price:

  • E-HSMT or E-HSYC preparation (Point c Clause 4): 0.2% of package budget (min 3,000,000 VND, max 60,000,000 VND).
  • E-HSMT or E-HSYC appraisal (Point d Clause 4): 0.1% of package budget (min 2,000,000 VND, max 60,000,000 VND).
  • E-HSDT evaluation (Point b Clause 5): 0.2% of package budget (min 3,000,000 VND, max 60,000,000 VND).
  • Selection result appraisal (Clause 6): 0.1% of package budget (min 3,000,000 VND, max 60,000,000 VND), including unsuccessful tenders.
  • Re-tender or similar packages (Clause 7): Document drafting and appraisal fees are capped at 50% of Clause 4 rates.

03. Track 2: Hiring an Independent Procurement Consultant (Point a Clause 2 & Circular 7/2026/TT-BNV)

Point a, Clause 2, Article 14 explicitly states that when hiring a procurement consultant, consulting fees are NOT bound by the rates in Clauses 3, 4, 5, 6, and 7. Instead, estimates are prepared using scope man-days, market consulting quotes, and Article 3 of Circular 7/2026/TT-BNV (effective 1 July 2026, replacing Circular 004/2025/TT-BNV on a 26-working-day monthly basis): Level 1 max 70,000,000 VND/month, Level 2 max 55,000,000 VND/month, Level 3 max 40,000,000 VND/month, and Level 4 max 30,000,000 VND/month, plus statutory management, employer insurance, logistics, and VAT.

Try both estimation modes instantly in the VNTender 2026 Cost & Consultant Salary Calculator.

Legal Basis & Regulatory Scope

Point a Clause 2 and Clauses 4 to 7 Article 14 of Decree 214/2025/ND-CP dated 04/08/2025; Article 3 of Circular 7/2026/TT-BNV dated 05/05/2026 (effective 01/07/2026).

Sources & Official References

Nghị định số 214/2025/NĐ-CP; Thông tư số 7/2026/TT-BNV